Project Schedule

Updated In-Depth Project Schedule – March 15, 2013

  • November 28, 2012 – Ground breaking
  • January 2013 – Construction begins
  • February 2013 – install footings
  • March 2013 – structural steel goes up
  • April 2013 – frame exterior walls
  • May 2013 – roof goes on
  • June 2013 – install fireplace
  • July 2013 – hang drywall
  • August 2013 – install tile flooring
  • September 2013 – install interior doors
  • October 2013 – pave parking lot
  • November 2013 – Completion of construction
  • December 2013 – Move in to building
  • January 2014 – Building open for dining and fitness services for Spring semester